Objective
This document will guide you through the steps to correct a wrong Fill operation, under Cashier -> My Ledger -> Insert Transaction.
Procedure
Fill lower than expected
In the last picture, the initial Fill was U$ 10,000.00. If the amount saved in this Fill operation was lower than the expected amount, you can simply insert a new Fill, and then the system will sum both amounts as shown in the three steps below.
1. Initial Fill of U$ 10.000,00 :
2. Insert a new Fill of U$ 5,000.00 :
3. New Fill shown by the system (sum of U$ 10.000,00 and U$ 5,000.00 = U$ 15,000.00) :
Fill higher than expected
On the other hand, if the value exceeds the expected Fill value, a user with Manager permission will have to delete the transaction under section Managements -> Ledgers / Cash Drawers.
Select the column View for the desired ledger
Click on the x to remove the undesired fill.
After that, a new Fill can be performed by the Cashier:
On the ledger the new balance will be shown:
Fill higher than expected (another possibility)
Instead of deleting the last Fill, there is a possibility to insert an Overflow transaction. In the example, it will be - U$ 3,000.00.
Then, the new balance will be U$ 5,000.00 (U$ 8,000.00 - U$ 3,000.00)